Срок оказания государственной услуги
1 consideration of the application for compliance with the Rules and forwarding the application to the authorized authority for subsoil study or a reasoned refusal - 10 (ten) working days
2 consideration of the application by the authorized authority for subsoil study and issuance of notification if necessary – 10 (ten) working days
3 refusal of the application by the service recipient or submission of amended information about the requested subsoil plot taking into account the comments of the authorized authority for subsoil study – 20 (twenty) working days
4 sending a notification by the service recipient to the authorized authority for subsoil study about the elimination of comments regarding non-compliance with Article 209 of the Code or sending an objection by the service recipient – 20 (twenty) working days
5 reconsideration by the authorized authority for subsoil study of the application for compliance of the boundaries of the requested subsoil plot with the requirements of Article 209 of the Code – 10 (ten) working days after receiving the notification from the service recipient
6 в случае согласования с уполномоченным органом по изучению недр границ запрашиваемого участка недр размещение уведомления направленного услугодателем услугополучателю о необходимости получения соответствующего экологического разрешения на операции по добыче, описанные в плане горных работ, проведения экспертиз и согласований плана горных работ и плана ликвидации в ЕПН– 2 (два) рабочих дня со дня направления уведомления услугополучателю
7 provision of the relevant environmental permit for mining operations described in the mining plan, conducting examinations and approvals of the mining plan and liquidation plan - 1 (one) year from the date of notification (if necessary, extension for 1 (one) year)
8 issuance of a license or a reasoned refusal - 5 (five) working days from the date of provision of the relevant environmental permit for mining operations described in the mining plan, conducting examinations and approvals of the mining plan and liquidation plan
Получатели услуги
Individuals and legal entities engaged in subsoil use activities
Результат оказания государственной услуги
Issuance of a license for the extraction of solid minerals or a reasoned refusal
Оплата
Payment is made in accordance with Article 727 of the Code of the Republic of Kazakhstan "On taxes and other obligatory payments to the budget (Tax Code)" except for the issuance of licenses under Article 201 and paragraph 11 of Article 277 of the Code